Westfield Stratford City


westfield-shopping_small

Project Background

Having previously successfully completed the Westfield London project SCS Group were employed to provide ventilation and fire protection systems to the underground car parks, loading bays and mall escape routes. Working in partnership with Flakt Woods UK , with a total contract value of more than £1m.


Project title Westfield Stratford City
Location Stratford, London
Project Value £1,000,000
Project Duration 12 Months

SCS Group’s Involvement

Managing the project to the tight programme was a challenge that the SCS site team rose to. Off site assembly was employed for the roof mounted extract plant and in some cases this was lifted by helicopter due to the sheer size of the 1.9 million sq ft site. All systems were commissioned, demonstrated and handed over in good time for the opening.

SCS Group’s Solution

SCS Group installed a pollution and smoke ventilation system to the underground car park with more than 200 jet fans, and 12 extract systems for the above ground areas with a site wide control network that integrated with the BMS and Fire alarm systems. SCS Group manufactured some 70 control panels all of which were acceptance tested at the Dorset manufacturing facility.